    Meeting Minutes
  • Corey/David will be working on the Tag Conduit and Modification Tool
  • Jon/Andy will be working on the Tag Search tool (main GUI)
  • Presentation
    • We need to allocate 1-1.5 hours to working on the presentation this week
    • We could talk about issues (file monitoring, context menu stall, David's attendance, scheduling issues at the beginning of the trimester)
    • Are we going to deliver and is the product we're delivering what we wanted it to be originally
    • Talk about development such as the command line tool
    • A status update for the project
    • The rest of the cycle 3 plan and the STRAT form
    • We've had some setbacks, but we're still on track
    • A list of slide assignments can be found here